The Water System Improvement Program (WSIP) consists of 87 projects - 35 local projects located within San Francisco and 52 regional projects, spread over seven counties from the Sierra foothills to San Francisco. The program is currently 91% complete. Here is a list of the projects that have been completed to date, or are in the Closeout Phase.

Project Cost Completed
San Joaquin Region
Lawrence Livermore Water Quality Improvement $4,198.480 7/31/13
Rehabilitation of Existing San Joaquin Pipelines $21,284,284 10/31/14
Tesla Treatment Facility $113,386,184 1/30/15
Sunol Valley Region
Standby Power Facilities - Various Locations $12,947,780 12/22/10
Alameda Siphon #4 $65,092,516 6/28/13
Pipeline Repair & Readiness Improvements $5,205,493 4/16/09
Calaveras Reservoir Upgrades $1,690,552 7/28/06
SVWTP Expansion & Treated Water Reservoir $129,629,223 10/31/14
San Antonio Pump Station Upgrade $12,893,496 6/29/12
Bay Division Region
BDPL Nos. 3 & 4 Crossover/Isolation Valves $27,011,834 7/31/09
SCADA System - Phase II $9,480,090 5/28/13
BDPL Reliability Upgrade - Relocation of BDPL Nos 1 & 2 $3,046,981 5/28/10
BDPL Nos. 3 & 4 Crossovers $30,313,550 6/30/14
SFPUC/EBMUD Intertie $10,581,799 3/20/14
BDPL No. 4 Condition Assessment PCCP Sections $1,966,891 2/6/09
Peninsula Region
Lower Crystal Springs Dam Improvements $34,931,425 12/28/12
New Crystal Springs Bypass Tunnel $81,460,035 8/17/12
Adit Leak Repair - Crystal Springs/Calaveras $2,787,322 7/31/08
Pulgas Balancing - Inlet/Outlet Work $1,765,938 5/11/06
Pulgas Balancing - Discharge Channel Modifications $2,911,617 7/30/10
Pulgas Balancing - Structural Rehab and Roof Replacement $20,232,215 12/28/12
Pulgas Balancing - Modifications of Existing Dechlor Facility $5,390,031 3/20/13
Cross Connection Controls $3,948,944 4/30/09
HTWTP Short-Term Improvements - Demo Filters $3,067,903 11/14/06
HTWTP Short-Term Improvements - Coagulation & Flocculation/Remining Filters $18,605,702 7/28/10
Capuchino Valve Lot Improvements $2,803,153 8/19/08
Crystal Springs/San Andreas Transmission Upgrade $200,779,599 6/30/15
Crystal Springs Pipeline No. 2 Replacement $56,054,876 12/31/14
San Andreas Pipeline No. 3 Installation $27,495,558 8/30/12
Baden and San Pedro Valve Lots Improvements $25,013,207 3/29/13
San Francisco Regional Region
Sunset Reservoir - North Basin $64,271,570 9/10/10
University Mound Reservoir - North Basin $43,318,898 3/29/13
Support Projects
Programmatic EIR $10,730,307 6/30/09
SF Local Region
Reservoirs
Sutro Reservoir Rehab & Seismic Upgrade (CLOSEOUT) $43,592,000 01/29/16 (Forecast)
Summit Reservoir Rehabilitation $12,989,600 09/28/12
Hunters Point Reservoir Rehab & Seismic Upgrade $3,521,000 10/31/12
Stanford Heights Reservoir Rehabilitation $23,641,004 04/01/11
Potrero Heights Reservoir Rehabilitation $6,836,736 08/11/08
Pump Stations/Tanks
Crocker Amazon Pump Station Upgrades $4,126,498 03/27/08
La Grande Tank Seismic Upgrade $6,987,728 12/18/08
Forest Hill Tank Rehab & Seismic Upgrade Seismic Upgrade $2,936,199 08/31/07
Forest Hill Pump Station Upgrades $7,388,789 07/01/14
Forest Knolls Pump Station Upgrades $6,196,797 01/18/12
Lincoln Park Pump Station Upgrades $4,345,215 08/11/08
Alemany Pump Station Upgrades (McLaren Park) $29,212,600 08/30/13
Mount Davidson Pump Station Upgrades $4,327,966 03/30/11
Palo Alto Pump Station Upgrades $6,127,118 11/16/10
Sky View - Aqua Vista Pump Station Upgrade $4,751,094 08/11/09
Summit Pump Station Upgrades $6,546,113 08/11/08
McLaren #1 Tank Rehab & Seismic Upgrade $4,659,741 08/11/08
Potrero Heights Tank Seismic Upgrade $1,084,863 08/11/08
Forest Knolls Tank Seismic Upgrade $3,546,789 01/18/12
Lincoln Park Tank Seismic Upgrade $2,690,656 08/11/08
McLaren #2 Tank Rehab & Seismic Upgrade $4,458,201 08/11/08
Mount Davidson Tank Seismic Upgrade $2,568,414 03/30/11
La Grande Pump Station Upgrades $5,171,622 03/29/13
Potrero Heights Pump Station Upgrades $605,670 08/11/08
Vista Francisco Pump Station Upgrades $5,142,600 01/31/13
Pipelines/Valves
North University Mound System Upgrade $10,000,010 06/30/11
Key Motorized and Other Critical Valves $10,984,746 08/11/08
Sunset Circulation Improvements $7,073,164 07/06/06
Lincoln Way Transmission Line $13,907,968 09/24/12
Noe Valley Transmission Main - Phase 2 $5,641,390 06/03/11
East / West Transmission Main $27,754,505 03/21/11
Fulton @ 6th $27,754,505 03/21/11
Miscellaneous
Vehicle Service Facility Equipment Safety Upgrade $27,754,505 03/21/11
Fire Protection @ CDD $1,675,476 01/30/07