San Francisco Public Utilities Commission
Skip to page body Home Customer Service How To Environment Projects & Programs About Us
BACK TO PROJECT LIST

 

Crystal Springs Pipeline No. 2 Replacement (WSIP)

Project Update
In December 2012, the Crystal Springs Pipeline No 2. Replacement Project reached substantial completion. Crews completed the remaining pipeline installation in November 2012. Once this work is finished, pipeline service work will begin. This work will take approximately two to three weeks,and will require the SFPUC Water Operations Team to begin flushing and cleaning the newly-rehabilitated pipeline before it is put back into service.

As of Nov. 2011, crews have successfully installed the last segments of the pipeline.tentative schedule.

Final road restoration on El Camino Real in the Burlingame area is scheduled for January 2013. Final completion for the project is anticipated for February 2013.

For the latest information and more details about construction in your neighborhood, please visit our project blog at www.sfwater.org/cspl2. You may also register your email address to receive the latest updates in your neighborhood. To enter your email address, look for the blue box in the right panel of this web page.

Check out this video to learn more about the project.

Project Description
 

SFPUC contractor Ranger Pipelines Inc. has replaced or repaired segments of a 19-mile pipeline known as Crystal Springs Pipeline No. 2. The work areas included intermittent sites along El Camino Real between Hillsborough, Burlingame and Millbrae. Other segments of work occurred in unincorporated sections of San Mateo County, Hillsborough, South San Francisco, San Bruno, Brisbane and Daly City.

The goal of this project was to ensure that our region’s water system infrastructure has a sustainable and reliable water supply. This pipeline was one of many water facilities in the region that had been identified for repair under the WSIP. Crystal Springs Pipeline No. 2 was installed between 1900 and 1930, and is one of the oldest and most critical water mains in the regional water system.

Some of the benefits of this project include:

  • Relocating sections of the pipeline to avoid unstable surface area surrounding the pipe
  • Retrofitting pipe bridge supports at two locations to withstand seismic events
  • Inserting new sections of pipes into existing pipeline to strengthen the pipe wall
  • Refining the water system to minimize the potential for corrosion of the pipeline
  • Replacing sections of the pipeline with thicker welded steel pipe

 

Project Information

  • CONSTRUCTION START
    March 2011
  • CONSTRUCTION FINISH
    March 2013
  • COST
    $59 Million
  • PROJECT PHASE
    Construction

Additional Information

The information shown reflects the current forecast information published in the latest WSIP Quarterly Report.

FACT SHEETS & CONSTRUCTION INFORMATION

 

Need More Information? Contact

Email: djaimes@sfwater.org or
Phone: (866) 973-1476.
After hours and weekends (866) 973-1476.

Sign Up for Our E-mail List
Email:

 

CSPL2 Replacement Project Blog