Project Description

The objective of the project is to rehabilitate portions of Moccasin Penstock by replacing steel pipe sections, encasing concrete anchor blocks, recoating penstock portions, and installing a electric valve actuators. The work is to be performed in Tuolumne, California.

Please note: The Engineer's estimate for the base work is $6,514,000. The Engineer's Estimate for all work including the additive alternate bid items is $8,047,000.

Bid discounts may be applied as per San Francisco Administrative Code Chapter 14B. The LBE Subcontracting Participation Requirement is 10.00%. Both San Francisco Small & Micro-LBEs and SFPUC-LBEs (Firms certified by SF Contract Monitoring Division) can be utilized to meet this requirement. The LBE sub-consulting participation requirement for this project is less than 20% because the Project is remote to San Francisco and requires specially manufactured items such as the items such fabrication of the large diameter penstock sections, bifurcation, air release valves, and valve actuator. Please contact Regina Chan at 415-551-4335 for further information.

Hard copy versions of plans, specifications and bidding documents are available at 525 Golden Gate Avenue, 1st Floor, Customer Service Desk, San Francisco, CA 94102 for a nonrefundable $190.00 fee bundled with a CD versionofthe plans, specifications and available project information and references.  paid by cash or by check payable to “SFPUC.” Call (415) 551-4603 for further information.  Visit http://sfwater.org/contracts for updates. Please be advised that prior to receiving these materials, all purchasers will be required to complete, sign and fully comply with a Confidentiality Agreement.

To request to receive plans, specifications and bidding documents by mail, a Contractor should mail the request to: SFPUC: Contract Administration Bureau at 525 Golden Gate Ave. 8th Floor; San Francisco, CA 94102. The request should include a contractor License number, a check in the appropriate amount made payabel to "SFPUC" and a FedEx Account number with return shipping information.  

  Addendum No. 6 was issued 12/04/17 and may be downloaded from the "Documents" tab, above.

Request for proposal

  • ESTIMATED COST
    $6,514,000
  • DUE DATE
    12/07/2017
  • DUE TIME
    2:00 PM
  • DURATION
    .
  • LOCATION
    525 Golden Gate Ave, 3/F Tuolumne Rm, SF, CA
  • CONTACT
    Contract Administration Bureau QBD@sfwater.org or (415) 551-4603

Pre-Bid Conference

  • DATE
    11/14/2017
  • TIME
    10:00 AM
  • ATTENDANCE
    Not Mandatory
  • LOCATION
    1 Lakeshore Drive, Administration Building Dining Room, Moccasin, CA. 95347
  • ADVERTISEMENT DATE
    11/06/2017