Bid Details
WD-2818
Sunol Valley Water Treatment Plant SCADA Server Room - BID TABULATION

Bid due

03/30/2017
2:00 PM

  • Type Construction
  • Department Wastwater Enterprise
BACK TO CONTRACTS & BIDS LIST
Project Description

The objective of the project is to convert an existing storage room into a Server Room. The Server Room will house existing SCADA servers, racks, and other related equipment. The project will have new power panels, conduits, chemical fire suppression, alarm, room upgrades, and air conditioning with rooftop condenser units. There will be modifications to the existing SCADA Room.

The LBE Subcontracting Participation Requirement is 20% and ONLY San Francisco (Local) Small & Micro-LBEs can be utilized to meet this requirement (Firms certified by SF Contract Monitoring Division).  SFPUC-LBEs cannot be utilized to meet the 20% LBE Subcontracting Participation Requirement. Please contact Marcus Lange at (415) 554-3106 for CMD related issues.

Hard copy versions of plans, specifications and bidding documents are available at 525 Golden Gate Avenue, 1st floor, Customer Service Desk, SF, CA 94102 for a non-refundable of $75 fee paid by cash or by check payable to "SFPUC". Call (415) 551-4603 for further information. A CD version is available to paid Plan holders only for an additional fee of $10. A contractor, who is requesting plans and specifications by mail, should send a request with the original, Signed Confidentiality Agreement, appropriate payment amount, FedEx number, business card, contractor License number and return shipping information to: Contract Administration Bureau at 525 Golden Gate Avenue, 8th floor. SF, CA 94102.

Addendum No. 1 was issued 3-14-17; it may be downloaded through the "Documents" tab. Please note that it does not contain attachments. These are only available to firms that have executed a Confidentiality Agreement.   
Addendum No. 2 was issued 3-27-17; it may be downloaded through the "Documents" tab. Please note that it does not contain attachments. These are only available to firms that have executed a Confidentiality Agreement.

Request for proposal

  • ESTIMATED COST
    $1 million
  • DUE DATE
    03/30/2017
  • DUE TIME
    2:00 PM
  • DURATION
    7 months
  • LOCATION
    525 Golden Gate Ave, 3/F Tuolumne Rm, SF, CA
  • CONTACT
    Contract Services (415)551-4603 or QBD@sfwater.org

Pre-Bid Conference

  • DATE
    03/10/2017
  • TIME
    10:00 AM
  • ATTENDANCE
    Not Mandatory
  • LOCATION
    Sunol Water Treatment Plan Admin Bldg. 8653 Calaveras Road, Sunol CA
  • ADVERTISEMENT DATE
    02/10/2017
LIST OF CERTIFIED LBE FIRMS AT HRC WEBSITE